Construction at our clinic site is back in full swing again, after a lull that came after the roof of the pharmacy building was poured. We’ve changed to a new construction team and they are working quickly to finish everything that needs to be completed for us to be a fully functional outpatient clinic. Below are photos of construction events from the past few weeks:
Completion of the stucco work on 3 storage areas under the pharmacy building:
Stucco work is almost completed on the inside of the pharmacy building:
In spite of periodic breakdowns, our faithful dump truck and driver continue to bring materials up to the site:
While the masonry was being done in the pharmacy building, another crew was digging a hole for a large septic tank. Here is the hole after a week of digging through rock and dirt:
Then, iron bars were laid to reinforce the floor, after which a concrete floor was poured:
Rock walls then went up and PVC pipes were put through the wall to allow for inflow of waste water into the tank:
Digging has also started on a 4-hole latrine for our patients:
Cherlie and I have entered into the construction arena as well, by beginning to paint the inside of the main clinic building. It already was painted with a coat of primer paint, but now we’re painting with the real colors! Here’s Cherlie showing how it’s supposed to be done:
We’ve been joined in our efforts each Saturday but 3 local young men:
We’ve appreciated the help and they’ve been happy to learn a new skill!