In the past week, the construction crew began working simultaneously on the clinic and pharmacy buildings. About 10 workers began digging the foundation of the pharmacy, while the masons continued to place blocks for the walls of the clinic throughout the week. On Friday, the carpenters began making formwork for the clinic columns, and the masons were able to pour 12 of the columns that day. Check out the progress:

Pharmacy Site

Digging the Pharmacy Foundation

Placing Blocks for Clinic Walls

Haitian Scaffolding

A Mason Checks His Level

Pouring a Clinic Column

“Boss Tony” – Foreman

Pouring Another Column

Clinic as of 9/01

 