Construction has again moved along at a nice pace in the past two weeks. In the clinic, workers finished pouring all concrete beams, which means the roof is up next! Tomorrow, Lord-willing, the carpenters will start the formwork for the roof, which should take a couple weeks. We recently stocked up on bamboo to use as supports for the formwork (50 dozen, to be exact).
The pharmacy has also changed quite a bit in the past two weeks. The foundation is now complete up to ground level, and while the carpenters are working on the roof formwork for the clinic in the next couples weeks, the masons will be able to finish placing rock for the pharmacy foundation and then pour the concrete floor. Let’s pray for a drier-than-usual rainy season!
Posted in Construction