Construction of the new clinic has continued at a promising pace this week. After pouring the concrete floor last week, the masons started placing blocks for the walls of the clinic on Tuesday, and as of yesterday, they had finished the 6th row of blocks.
We were also able to lay out the pharmacy building yesterday (adjacent to the clinic), and we hope to start digging the foundation early next week.
We are so excited about all the progress that has been made in the past two weeks, and we are hopeful that it will continue in the coming weeks.